Timeline

The Justice System Improvement Program (JSIP) is a multi-year project spanning 10 years. The following is an overview of major milestones.

Timeline

2018
January

County commissioners approve funding for comprehensive assessment

» Read moreRead more
February

Community engagement forums and workshops

» Read moreRead more
2019
January

JSIP assessment completed

» Read moreRead more
2020
February

Conceptual predesign begins

» Read moreRead more
December

Advisory committees formed

» Read moreRead more
2021
April

Conceptual designs finalized

» Read moreRead more
July

Pretrial Services expanded and Crisis Outreach pilot programs launched

» Read moreRead more
December

County receives matching grant for new courthouse

» Read moreRead more
2022
January

Community Safety and Justice Campus site selected

» Read moreRead more
February

Crisis Center site finalized

» Read moreRead more
March

County to receive $1 million for new Emergency Operations Center

» Read moreRead more
March

Historic Courthouse Advisory Committee convened

» Read moreRead more
June

Gerding Builders selected to build Crisis Center

» Read moreRead more
July

Courthouse design process begins

» Read moreRead more
July

Mahlum selected to design Crisis Center

» Read moreRead more
August

DLR Group selected to design courthouse

» Read moreRead more
September

Site master plan completed for Community Safety and Justice Campus

» Read moreRead more
September

Community Engagement Forum – Mental Health in the Justice System

» Read moreRead more
October

Community Safety Forum

» Read moreRead more
2023
January

Bond Measure package finalized

» Read moreRead more
February

JSIP Open House

» Read moreRead more
May

Proposed bond measure on ballot

» Read moreRead more
2024
May

Crisis Center services to begin

» Read moreRead more